Wednesday, November 27, 2013

Shoreline stabilization update - Wednesday, Nov 27


Managed to make some progress on the stairway this week, in between the rain and snow.

Building concrete block wall for stairs support

Finished block walls


Filling up between the walls with sand and rubble to support the step pours.

 Have a very Happy Thanksgiving  !

Friday, November 22, 2013

Shoreline Stabilization update - Friday, Nov 22

Stairway under construction.  Stepped footings have been completed. Next step: laying concrete block on top of the footings to create the sides of the stairway. 

Using a string line to establish a reference for the stairway slope and elevation

Since we had the skid steer for one more day, Steve used the machine to begin cutting a wide terrace just above the top edge of the rip-rap stone.  The finished concrete stairway will exit onto this terrace (will post photos of terrace under construction soon).  

Tuesday, November 19, 2013

ShorelineStabilization update - Tuesday, Nov 19

 All the rip rap is complete, save the area bordering the concrete stairway, which will be completed after the steps have been formed and poured.

Competed rip rap


Steve suckin' leaves 






Poured the first two levels of the stairway footings today
Sunset, Lake Nottely

Saturday, November 16, 2013

Shoreline Stabilization update - Sunday, Nov 17

Take a ride with our Heavy Equipment Operator on the skid steer 


Up the hill for more stone....


....fill the bucket....



....back down the hill with the stone.....


....and dump

and repeat ( ....until the pile is gone ! )

Shoreline Stabilization update - Saturday, Nov. 16


Friday - Rolling out geotextile fabric 

Fabric rolled out and staked down
Saturday AM - Heavy Equipment Operator Steve dumping rip-rap stone 
Shoreline rip-rap in progress
End of Day 1 rip-rapping

Thursday, November 14, 2013

Shoreline Stabilization update - Thursday, Nov 14



This is Breeze, Jim Haskin's dog.  She comes to see me every day while I'm working down at the shoreline. She's just a puppy. Her favorite game is to grab a tool out of my bag and run off with it.  Jim says she's a little clepto.  Several of my tools have gone missing since she started coming to visit. 

Tuesday, November 12, 2013

Shoreline Stabilization update - Tuesday, Nov. 12

The first two truckloads of rip-rap stone were delivered today  ( the job should take 4 1/2 dump truck loads ). Staged the stone in the driveway. 


From there, we'll move it down to the shoreline with the skid-steer machine.

A family of Mallard ducks stopped by yesterday to check out my progress.

    

Sunday, November 10, 2013

Shoreline Stabilization update - Week 1

The shoreline has been reshaped, and a reasonable slope has been established. Here's a few photos of the work so far.

TVA 26A permit posted

Undercut shoreline before reshaping


Shoreline with new slope, ready for rip-rap

Checking the slope using inclinometer app


The bottom section of footings - steel-reinforced concrete foundations which anchor the stairway to the lake bed  - have also been dug.